Tandridge provided an update to the Inspector advising that they expected to be in a position to respond by 5 Jan 2022 by which time they hoped to have received the appropriate detail from their transport consultants (see TED49 Nov 2021)
13 September 2021: Tandridge received a reply from the Inspector (ID19 - Sept 2021) in response to their letter. This would now seem to inevitably lead to a new Local Plan being necessary with maybe Tandridge needing to revert to a housing supply via several smaller sites (as suggested in para 11 of this latest letter).
27 August 2021: Tandridge sent an update (TED48) to the Inspector on the latest delay with the high-level transport modelling This letter proposes the actions they will be undertaking to address the issues raised by Surrey County Council and Highways England. They will also propose an alternative option prompted by the ongoing delay to the traffic modelling and regarding the August timeframe.
19 July 2021: Tandridge wrote to the Inspector (TED47) to update him on the Council’s thoughts on how to progress the Local Plan Examination. They also provided him with a Statement which outlines the initial findings of the assessment of potential mitigation measures for Junction 6 of the M25.
30 June 2021: Tandridge sent a response outlining the progress of the high-level transport modelling work and the decision-making process TED46 Update to Inspector.